热控盘柜安装Thermalcontrolpanelinstallation施工作业指导书ConstructionWorkInstruction施工作业指导书审批表Constructionworkinstructionapprovalform技术准备开始制作、安装前,查阅集控室、电子间布置图,了解施工过程中热控中盘箱、柜的数量,核算工作量,提出材料计划;并与土建、机务专业图纸核对,检查盘箱、柜的位置、尺寸是否与其他专业设备、管道等布置有冲突,如有矛盾汇总后提交专业工程师,由专业联系设计院出设计变更;检查与盘联系的电缆主通道设计是否畅通,保证与电气专业的接口正确Technicalpreparation:BeforestartingtheproductionconsulttheCCRandelectronicequipmentroomunderstandthenumberofICdevicesboxesandcabinetsduringtheconstructionprocessstatisticsvoluneoftheprojectandsubmitthematerialplan;thencheckthedrawingsofcivilandmechanicalandcheckwhetherthepositionandsizeoftheplateboxandcabinetcollisionwithotherprofessionalequipmentsandpipelayout.IfthereisanycontradictionsubmitittotheprofessionalengineerafterthesummarychangethedesignbythecollisionengineerdesigninstituteandcheckthecableMainchanneldesignissmoothtoensurethattheelectricalinterfaceiscorrect..开箱查验会同厂家,物资,项目部专业人员共同开箱检查,盘面应平整,内外表面漆层应完好;盘柜的外形尺寸、仪表安装孔尺寸、盘装仪表和电气设备的型号及规格等应符合设计,配件齐全ArrivedInspection:Totogetherwiththevendorprocurementprojectstafftounpackingacceptancethecabinetssurfaceshouldbesmoothinteriorandexteriorsurfaceshouldbeintact.cabinetsenclosure
5.3盘柜底座制作工序卡ManufacturingprocesscardforPanelbaseproduction.底座制作完成后,将附着在焊缝上的药皮清理干净Afterthebaseismadethemedicineskinattachedtotheweldshouldbecleaned..用铁刷子将底座内外表面的铁锈清理干净Usinganironbrushtocleanuptherustontheinsideandoutsideofthebase..将器皿中的防锈漆用油漆刷调匀,然后在底座的焊口处均匀、完整地涂刷防锈漆,待防锈漆晾干之后再均匀地涂刷银粉漆Thepaintusedinthevesselisthoroughlymixedwiththepaintingbrushtheninthebaseoftheweldedjointsevenlycompletebrushingantirustpainttopaintdryandthenevenlybrushingsilverpaint.
5.4热控盘柜底座安装工序卡Cabinetbaseinstallationprocesscard
5.5热控盘柜的运输工序卡:Containertransportprocesscard
5.
6.热控盘柜安装工序卡Cabinetinstallationprocesscard
5.
7.热控盘柜验收及防护工序卡EnclosureacceptanceandProtectionprocesscard
1.安装完成后,施工单位负责质量自检一级验收并填写ITP检查验收表和相应的技术记录Aftertheinstallationiscompletedtheconstructioncompanyneedtoqualityself-testandfillintheITPandinspectionsheetsformandthecorrespondingtechnicalrecords.2•自检合格且资料齐全、完整后,向专业提交自检资料进行二级验收验收应对上一级验收的各项具体要求进行复测,核查资料是否符合要求,施工负责人必须陪同对于验收过程中发现的质量问题应及时整改,整改合格后要按相关程序反馈后重新进料(RFI),由专业验收后提交QC部室进行三级验收,验收完毕无误后其联系业主进行四级验收Whentheself-inspectionqualifiedandcompletedwewilltakematerialofself-inspectiontodepartmentforthesecondinspection.Inspectionshouldberecheckedtheinspectionofthespecificrequirementsofthefirstinspectionandtheverificationdataconformtotherequirements.Forthequalityproblemsfoundintheinspectionprocessshouldberectificationontimeaftertherectificationofqualifiedtorecheckagainwiththerelevantprocedures.AfterinspectedtheconstructionteamneedtotaketheRFIfordepartmentengineertoinspectandthentaketheRFTfortheQCdepartmentAftertheinspectioniscompletedcontacttheownerforthefourthinspection..全部验收合格后,应对盘(台、箱、柜)进行防护布置在室外的盘、台、保温/保护箱、接线盒,可先用防火篷布包裹,再用木板制作防护外罩,扣在设备外侧,用于防砸,防雨AftertheinspectionforpanelinstallationshouldbethepanelTrayboxescabinetsforprotection.ArrangedintheoutdoorplatecabinetinsulationprotectionboxjunctionboxwecanusefiretarpaulintowrapthenusewoodtomakeprotectivehousingstoProtectionbuckleontheoutsideoftheequipmentforpreventingandraining..盘台四周拉设安全绳,张贴醒目标志,提醒现场施工人员注意成品保护Takingsafetyropeandmarkedsigharoundtheplatetoremindtheconstructionsiteworkerspayattentiontoproductprotection.注Note防护整齐美观Tidyandbeautifulprotection.
6.0强制性条文执行内容Contentofcompulsoryprovisionsofengineeringconstructionstandards《工程建设标准强制性条文》执行计划表ProjectConstmctionStandardMandatoryProvisionsimplementationplan安全文明施工保障措施及风险控制计划表Safetyandcivilizationconstructionguaranteemeasuresandriskcontrolplanlist安全施工措施Safetyconstructionmeasures进入施工现场的施工人员必须穿戴合格的劳保用品并正确佩戴安全帽严禁穿拖鞋、凉鞋、高跟鞋或带钉的鞋,以及短袖上衣或短裤进入施工现场严禁酒后进入施工现场所有参加施工人员必须认真学习《电力建设安全工作规程》有关内容并进行体检和安全三级考试合格后方可上岗,在施工前进行安全交底,并有签字记录Theconstructionworkersenteringtheconstructionsitemustwearqualifiedprotectionclothesandwearsafetyhelmetscorrectly.Cannotwearslipperssandalshighheelsornailedshoesandshort-sleevedshirtorshortsintotheconstructionsite.Noalcoholintotheconstructionsite.Allparticipatingconstructionworkersmustconscientiouslystudytherelevantcontentsofthe《CodeofConductforSafetyinElectricPowerConstruction^conductphysicalexamsandsafetyexamsbeforepassingtheexamsandsubmitsafetyrecordsbeforeconstructionandsigntherecords.
8.
1.
27.
1.2电动工具使用前检查绝缘、线路和接地,保证性能良好施工现场中的临时用电场所,有明确的保护系统,符合三级配电两级保护要求,必须做到“一机,一闸,一保护”,线路架设符合规定Beforeweusepowertoolstochecktheinsulationwiringgroundingandperformanceiswell.Thereisadefiniteprotectionsystemforthetemporarypowersupplysitesintheconstructionsitewhichmeetstherequirementsofthetwo-levelprotectionforthethree-leveldistributionandmustbenonemachineonebrakeandoneprotection1andtheerectionofthelinesmeetstherequirements.正确使用电动工器具,防止使用方法不当而导致伤害CorrectuseofelectrictoolsPreventtheuseofimpropermethodsandcauseharm.施工用临时电源要安全可靠,尽量采用可靠移动式电源箱;电源电缆使用适当,电流、电压容量满足负荷要求,避免有中间接头Theconstructionoftemporarypowersupplytobesafeandreliabletrytouseareliablemobilepowersupplybox;powercablesuseappropriatecurrentvoltagecapacitytomeettheloadrequirementsAvoidtheintermediateconnector.雷雨、大风天气严禁高空作业,防止雷击或高空坠落事故的发生Thunderstormwindyweatherisstrictlyprohibitedathighaltitudetopreventtheoccurrenceoflightningoraltitudecrashes.夏季施工做好防暑降温措施,预防中暑事件发生本项目在露天作业及劳动强度较大,尽量避免安排在37℃以上气温条件下施工,防止因气温过高或在阳光下暴晒出现中暑和其它意外事故TheconstructionworkersshouldmakemeasuresofpreventsummerheatstrokeinSummer.Becauseofthisprojecthasgreatopen-airoperationandlagerworking.Sothatweshouldbeavoidedfrombeingarrangedunderthetemperatureabove37℃topreventheatstrokeandotheraccidentsduetoover-temperatureorsunexposure.吊装和运输时,应轻搬轻放,并绑扎牢固,防止倾斜和碰撞,吊运时应有起重工指挥,专人监督、统一口令,防止设备落下损坏,伤人伤物WhenwetakeHoistingandtransportationweshouldbelighttocarryandlashingfirmlytopreventtiltandcollisionweshouldtakecraneconductorsupervisionunifiedpasswordtopreventdamageequipmentwoundinginjury.现场所用电源线、电焊皮线走向整齐合理Thepowerlineandweldingleatherlinewhichwillusedtoneatandreasonable.夜间施工场所必须有充足的照明Adequatelightingisrequiredatnightconstructionsites.施工人员应熟悉现场环境,正确佩戴安全帽防止磕碰、高空落物Installationpersonnelshouldbefamiliarwiththewearhelmetstopreventbumpandhigh-altitudefallingobjects.安全文明施工部分:Safetyandcivilizedofconstruction施工现场应保持整洁,垃圾、废料应及时清除,做到“五清”,对施工用料要堆放整齐,坚持文明施工ConstructionsiteshouldbekeptcleaningandthegarbagewasteshouldbepromptlyremovedontimeweshoulddothefiveclearTheconstructionmaterialsshouldbeneatlystackedandtokeepcivilizedconstruction.盘柜运输、安装时,加垫胶皮,注意保护电子间、主控室墙面、地面,防止二次污染Weneedtopadrubberwhentransportedandinstallationpanelspayattentiontoprotecttheelectricalbuildingthemaincontrolroomwallandthegroundtopreventtwotimespollution.盘柜开箱后的包装板交工地物资部回收处理,包装带、包装覆盖物及时清理,按类丢弃AftertheopeningofthepanelthepackingboardshallbehandedovertotheMaterialsDepartmentofthesiteforrecyclingthepackingtapeandthepackagingcoveringshallbecleanedintimeanddiscardedaccordingtotheclass.施工人员保护好各自的盘、台、柜、箱及内部的设备,防止小件被盗、外表油漆被划,做好设备的防护工作Installationpersonnelshouldprotectpanelscabinetsplatesandinternalequipmentandtopreventsmallpiecesstoleniftheappearanceofpaintiszonedwewilldoagoodjobforequipmentprotection.注意节能降耗,下班后将电源切断,防止设备空转Payattentiontosavingenergyandcuttingoffthepoweraftergetoffworktopreventtheequipmentfromidling.风险控制计划表:RiskControlScheduleHSE风险评估表HSERiskandImpactAssessmentHSERIAForm目录TableofContents
1、编制依据11Reference
12、概述
12、Summary
13、主要工程量
23、Mainworkquantity
24、作业条件34Workcondition
35、作业方案
65、Workscheme
66、强制性条文执行内容
206、Contentofcompulsoryprovisionsofengineeringconstructionstandards
207、安全文明施工保障措施及风险控制计划表
217、Contentofcompulsoryprovisionsofengineeringconstructionstandards
218、质量控制措施
388、Qualitycontrolmeasures
389、绿色施工措施
389、GieenConstructionmeasuies3810应急保障措施4010Emergencysupportmeasures
401、编制依据
1、Reference
1.1《电力建设施工技术规范第4部分热工仪表及控制装置》DL
5190.4-2019:《ElectricPowerConstructionTechnicalSpecificationPart4:Thermalinstrumentandcontroldevice》DL
5190.4-2019:《电力建设施工质量验收及评价规程第4部分:热工仪表及控制装置》DL/T
5210.4-2018:《Codeforacceptanceandevaluationofconstructionqualityofelectricpowerconstruction^Part4:ThermalinstrumentsandcontroldevicesDL/T
5210.4-2009:《电力建设安全工作规程》DL
5009.1-2014:《Codeforsafetyofelectricpowerconstruction^DL
5009.1-2014:《建设工程质量管理条例》国务院令第279号^RegulationsonqualityManagementofconstructionworks》orderNo.279oftheStateCouncil::《工程建设标准强制性条文》电力工程部分2017年版《Mandatoryprovisionsofengineeringconstructionstandards》Part2017editionofPowerEngineering:《国家电网公司基建安全管理规定》《StateGridCorporationinfrastructuresafetyManagementRegulations^《防止电力生产事故的二十五项重点要求》2017年版《25keyrequirementsforpreventionofelectricityProductionAccidents》n2017edition江设计院及厂家提供的关于本项目工程的图纸ThedrawingsofthisprojectprovidedbyZhejiangDesignInstituteandmanufacturers:
2、概述2\Summary本工程为孟加拉国库尔纳330MW200-300MW双燃料联合循环电站项目,施工内容为库尔纳项目热控全厂盘柜安装工作内容主要包括集中控制室、工程师室、电子设备间、辅助控制室等控制盘柜安装Theprojectis:BangladeshKhulna330MW200-300MWcombinedcycleduelfuelpowerplantprojectTheconstructioncontentistheinstallationofthermalcontrolpanelsinthewholeplantoftheKhulnaproject.Theworkmainlyincludestheinstallationofcontrolpanelsinthecentralizedcontrolroomengineerroomelectronicequipmentroomandauxiliarycontrolroom.
8.0质量控制措施Qualitycontrolmeasures盘底座制作下料严禁气割火焊Panelbaseproductingthegasweldingisstyictlyprohibited.盘底座制作必须在施工组合平台进行Panelbaseproductionmustbecarriedoutintheconstructionofcombinationplatform.底座制作防腐必须刷方块漆Panelbasemadeofanti-corrosionmustbepaintedsquarepaint.盘底座在安装后及盘柜安装前必须进行防护防止污染Aftertheinstallationofthepanelbaseandtheinstallationofthecabinetmustbeprotectedagainstpollution.盘底座必须两点接地Thepanelbasemustbegroundedattwopoints.盘台的运输和安装过程,不准损坏盘台的油漆层及地面墙角等土建已完工项目Whenthetraytransportandinstallationwearenotallowedtodamagethepaintlayerofthefloorandthegroundcornerconstructionprojectshavebeencompleted.盘、台必须使用螺栓固定牢固,严禁焊接Thepanelandthecabinetmustbetousetheboltfixedfirmlynotforbiddentoweld.盘、柜安装后不得在其上进行引起剧烈震动的工作Panelcabinetinstallationshallnotbecarriedoutonitsviolentvibrationcausedbythework.盘、柜应有明显接地,且接地牢固可靠Panelcabinetshouldbegroundedandthegroundissolidandreliable.所有盘柜安装后必须防护到位Allcabinetsmustbeprotectedinplaceafterinstallation.盘底座及盘柜安装完成后必须进行三级验收Whentheinstallationofpanelandjunctionfinishshuldbeacceptingofthethird.绿色施工措施Greenconstructionmeasures严格把控施工废料的回收,维持现场“绿色环境”加大对施工废料的回收和利用,一方面提高施工用料的利用效率,减少单位工程量所产生的施工废料;另一方面加大现场环境管控,严格做到文明施工,做好“工完料尽场地清”;维护现场“绿色环境”Strictlycontroltherecyclingofconstructionwasteandtomaintainthengreenenvironment0:Increasetherecyclinganduseofconstructionwasteontheonehandwecanimprovetheuseofconstructionmaterialsandreducetheamountofconstructionwastegeneratedbytheprojectquantity;Ontheotherhandweneedtostrengthentheon-siteenvironmentalcontrolandstrictlycivilizedconstruction.Soweshoulddoagoodjobinthefieldof“clean;GreenenvironmentH.因现场交叉施工极易造成盘柜的二次污染,就地安装的盘柜完毕必须及时防护,确保设备不被破坏污染,保持本色不变,同时做好防护宣传工作BecauseofthesiteofcrossconstructioniseasytocausetwooftheenclosureofpollutionOnthespotofthecabinetinstallmustbetimelyprotectiontoensurethattheequipmentisnotdestroyedpollutionmaintainthesamecoloranddoagoodjobforprotectingandpublicizing.加强油漆、稀料等物品的存放与管理,盛装油漆的容器要密闭防止泄露,使用过的油漆毛刷要统一回收,调和油漆时避免抛洒在地面上污染土壤;现场油漆施工时,作业区下部必须铺设隔离物,以防治污染地面和设备,油漆作业不准将沾有稀释品、油漆的棉纱乱抛弃,废旧的刷子、手套、破布等消耗品必须放置在不可利用的废旧物回收箱内,不可随处乱扔,以防止对环境造成污染Strengthenthestorageandmanagementofpaintsthinnersandotheritemsthepaintcontainerscontainingpainttobesealedtopreventleakagetheuseofthepaintbrushtoaunifiedrecoverytoavoidmixingthepaintspilledonthegroundcontaminatedsoil;sitepaintconstructionthelowerpartoftheworkareamustLayingpartitionstopreventpollutionofthegroundandequipmentpaintoperationsarenotallowedtobecontaminatedwithadilutionpaintcottonlitterdiscardedwastebrushesglovesragsandotherconsumablesmustbeplacedintheunavailablewasterecyclingboxnotLittereverywheretopreventpollutionoftheenvironment.尽量避免或减少施工过程中的光污染夜间室外照明灯加设灯罩,透光方向集中在施工范围电焊作业采取遮挡措施,避免电焊弧光外泄Trytoavoidorreducethelightpollutionduringconstruction.Thenightoutdoorilluminationlampaddsthelampshadethelighttransmissiondirectionconcentratesintheconstructionscope.Shieldingmeasuresareadoptedtoavoidweldingarcleakage.施工中选择能耗低、性能好,技术含量高、噪音低、安全系数较高的小型电动工器具对有可能发生尖锐噪音的小型电动工具,如冲击钻、磁力钻、磨光机等,严格控制使用时间控制使用的频次的设备数量,在夜间休息时减少或不进行作业Constructionselectionoflowenergyconsumptiongoodperformancehightechnologylownoisehighsafetyfactorofsmallelectrictools.Forsmallpowertoolsthatmaycausesharpnoisessuchasimpactdrillmagneticdrillgrinderetc.strictlycontroltheuseoftimethenumberofdevicestocontrolthefrequencyofusetoreduceornottoworkatrestatnight.在现场材料及设备运输作业中,控制运输工具发出的噪音的材料、设备搬运、堆放作业中的噪音,对于进入场内的运输工具,要求发出的声响符合噪音排放要求Inthefieldofmaterialandequipmenttransportoperationscontrolthenoiseemittedbytransportvehiclesequipmenthandlingstackingoperationsofnoiseforaccesstothefieldoftransportvehiclestherequiredsoundtomeetthenoiseemissionrequirements.采用有利于绿色施工开展的新技术、新工艺、新材料、新设备、新流程以及电力五新技术,形成效果显著的社会成果;发展适合绿色施工的资源利用与环境保护技术,对落后的施工方案进行限制或淘汰,鼓励绿色施工技术队额发展,推动绿色施工技术的创新AdoptingnewtechnologiesnewprocessesnewmaterialsequipmentnewprocessesandfivenewtechnologieswhicharebeneficialtogreenconstructiontoformsocialachievementswithremarkableeffecttodeveloptheresourceutilizationandenvironmentalprotectiontechnologysuitableforgreenconstructiontolimitoreliminatethebackwardconstructionschemesandtoencouragethedevelopmentofgreenconstructionTechnologyteamPromotetheinnovationofgreenconstructiontechnology.应急保障措施Emergencysupportmeasures根据事件性质启动不同等级的应急响应方案,现场办公区设立应急指挥小组,并在现场办公区设应急急救站,在现场办公区设立施工人员应急集合点AccordingtothenatureoftheeventtostartdifferentlevelsofemergencyresponseplanConstructiondistrictsetupEmergencycommandTeamandinthefieldofficeareatosetupemergencyfirstAidstationinthefieldofficeareasetupconstructionpersonnelemergencypoints.一旦现场发生紧急事故,由相关人员立即报告应急指挥小组,同时第一时间通知应急值班人员,根据现场情况划定警戒区,疏通抢救进出道路,并将无关人员集中至集合点,清点后按预定疏散路线疏散OncethesceneofanemergencybytherelevantpersonnelimmediatelyreporttotheemergencyCommandteamandthefirsttimetoinformtheemergencydutypersonnelaccordingtothesituationonthescenedesignatedalertareadredgetherescueandaccessroadsandnottofocusonthecollectionpointinventoryaftertheevacuationroutescheduledevacuation.现场人员视情况对伤员进行应急处理或抢救,需要去医院抢救的,应立即送往医院Fieldpersonneldependingonthesituationofthecasualtyemergencytreatmentorrescueneedtogotohospitalrescueshouldbesenttothehospitalimmediately.发生触电事故时,现场人员第一时间报警,通知本单位,并实行自救,当触电事故发生后,必须不失时机的进行抢救,动作迅速方法正确,使触电者尽快脱离电源是救治触电者的首要条件防止触电者脱离电源后可能的摔伤,特别是当触电者在高处的情况下,应考虑防摔措施人触电后,会出现神经麻痹、呼吸中断、心脏停止跳动等征象,外表上呈现“假死”状态,不能马上送到医院时,应立即现场急救方法是人工呼吸法和胸外心脏挤压法Anelectricshockaccidentthescenepersonnelthefirsttimetoalarmnotifythecompanyandimplementself-helpwhentheelectricshockaccidentmusttocarryouttherescuenotimequickMethodcorrectsothattheelectricshockfromthepowersupplyisthefirstconditionforthetreatmentofelectricshock.Preventtheelectricshockpersonfromthepowersupplyafterthepossibilityofthefallespeciallywhentheelectricshockinthecaseofhighshouldconsiderthemeasurestopreventfalling.Peopleafterelectricshocktherewillbeparalysisrespiratoryinterruptioncardiacarrestandothersignstheappearanceofsuspendedanimationnstatuscannotbeimmediatelysenttothehospitalshouldimmediatelyon-sitefirstaid.Methodsareartificialrespirationmethodandchestheartextrusionmethod.当发生火灾时,现场人员第一时间报警,通知本单位,并实行自救,火势很小,可以用手提灭火器、消防水源进行补救救人重于救火,火场上如果有人受到火势威胁,首要任务是把被火围困的人员抢救出来先控制、后灭火,对于不可能立即扑灭的火灾,首先控制火势的继续蔓延扩大,在具备扑灭火灾的条件时,展开攻势,扑灭火灾灭火中应防止爆炸、坍塌、坠落伤亡等事故Whenafireoccursthesitepersonnelthefirsttimetoalarmnotifythecompanyandimplementself-helpiffireissmallerwecanuseportablefireextinguishersfirewatersourceforremediation.Savemorethanthefireonfireifsomeoneisthreatenedthefirsttaskistobethesiegeofthepeoplerescued.Firstcontrolfirethenexterminatefireforthefirecannotbeextinguishedimmediatelyfirsttocontrolthespreadofthefirecontinuestoexpandinthecaseoffireconditionslaunchedanoffensivetoextinguishthefire.WhenexterminateFireshouldpreventexplosioncollapsefallcasualtiesandotheraccidents.机械外伤一般是直接损伤,有时并不十分严重,但是由于伤后抢救处理不当,往往会加重损伤,造成不可挽回的严重后果重伤员运送应用担架,腹部创伤及脊柱损伤者,应用卧位运送;胸部伤者一般取卧位,颅脑损伤者一般采取仰卧偏头或侧卧位抢救失血者,应先进行止血;抢救休克者,应采取保暖措施,防止热损耗Mechanicaltraumaisadirectinjurysometimesnotveryseriousbutbecauseoftheinjuryafterthetreatmentofimproperoftenaggravatedinjuryresultinginirreversibleseriousconsequences.Theheavycasualtytransportstheapplicationstretchertheabdomenwoundandthespineinjuryappliesthehorizontalpositiontocarrythechestcasualtygenerallytakestherecumbentpositionthecraniocerebralinjurypersongenerallyadoptssupineorside-lyingposition.Thosewhorescuebloodlossshouldstopbleedingfirstandrescueshockshouldtakewarmmeasurestopreventheatloss.发生高空坠落事故时,现场人员第一时间报警,通知本单位,并实行自救,当发生高处坠落事故后,应优先对呼吸道梗阻、休克、骨折和出血上进行处理,应先救命,后治伤重伤员运送应用担架,腹部创伤及脊柱损伤者,应用卧位运送;胸部伤者一般取卧位,颅脑损伤者一般采取仰卧偏头或侧卧位抢救失血者,应先进行止血;抢救休克者,应采取保暖措施,防止热损耗;抢救脊椎受伤者,应将伤者平卧放在帆布担架或硬板上,严禁只抬伤者的两肩与两腿或单肩背运Intheeventofahighaltitudefallaccidentthescenepersonnelfirstalarmnotifytheunitandimplementself-helpwhenaheightfallaccidentshouldgiveprioritytorespiratorytractobstructionshockfractureandbleedingonthetreatmentshouldfirsthelpaftertreatment.Theheavycasualtytransportstheapplicationstretchertheabdomenwoundandthespineinjuryappliesthehorizontalpositiontocarrythechestcasualtygenerallytakestherecumbentpositionthecraniocerebralinjurypersongenerallyadoptssupineorside-lyingposition.Therescueofbloodlossshouldbefirsttostopbleeding;Rescueshockshouldtakewarmmeasurestopreventheatloss;torescuetheinjuredspinetheinjuredshouldbeplacedonacanvasstretcherorahardcardboardonlytocarrytheinjuredtwoshouldersandtwolegsorsingleshoulder.
3、主要工程量Mainworkquantity3」施工范围主要包括集中控制室、工程师室、电子设备间、辅助控制室、以及所属标段内热控盘柜安装Constructionscope:Itmainlyincludesthecentralizedcontrolroomtheengineerroomtheelectronicequipmentroomtheauxiliarycontrolroomandtheinstallationofthethermalcontrolpanelinthesubordinatebidsection.主要工作量
3.2Mainworkquantity
4.0作业条件Workcondition备注Remarks
5.0作业方案Workscheme
5.1施工工序流程图Constructionprocessflowchart
1.施工准备Constructionpreparation
2.盘底座制作Panelbaseproduction3盘底座安装Panelbaseinstallation4盘柜运输Paneltransport
5.盘柜安装panelinstallation
6.验收Panelinspection
5.2施工前准备工序卡PreparationprocessCardbeforeinstallation操作方法Methodsofoperation序号及步骤名称Serialnumberandstepname主要作业方法和操作要求Mainoperatingmethodsandoperationalrequirements工艺质量要求Processqualityrequirements作业项目名Jobname热控盘柜安装Thermalcontrolpanelinstallation编号No.编制Preparedby签名signature日期date专业审核Departmentreview签名signature日期date项目审批工程engineering签名signature日期date质量quality签名signature日期date dimensionsinstrumentmountingholesizecabinetinstrumentandelectricalequipmentmodelandspecificationsShouldbeconsistentwiththedesignshouldbecompleted..现场复核随着土建、机务安装进度,适时去现场核实,提请土建专业预留孔洞、预埋铁件,配合土建、机务预埋进盘电缆保护管Siterecheck:Withthecivilconstructionofmechanicaldepartmentandcivildepartmentinstallationprogresstimelytothescenetoverifycivildepartmenttoreserveholesembeddedironpieceswithcivilengineeringmechanicalprocesstoinstallintotheconduitsandcabletrays..人员配备详见作业条件,对所有施工人员进行技术和安全交底,并做好签字记录Personnelequippedwiththeoperatingconditiontotakesafetyandtechnologyexplanationforworkerandtomakesignaturerecordbeforeworking..机具配备详见作业条件equipmentseeoperatingconditions.
2.设备材料领取运输Equipmentmaterialtoreceivetransportation.从钢材库领取槽钢、角钢等材料FromthesteelhousetoreceivetheChannelsteelAnglesteelandothers..从焊材库领取焊条、油漆等材料Fromtheweldinglibrarytoreceiveelectrodespaintsandothermaterials..从设备库领取需安装的热控盘、台、柜FromtheequipmentlibrarytoreceivetheinstallationofICpaneldeskandcabinets.注Note所有设备、材料的质量、型号规格要符合图纸设计要求及国家质量标准和规范,且经过报审及业主验收AlltheequipmentqualityofmaterialsmodelspecificationstomeettheDrawingsdesignNationalqualitystandardsandnormsandafterthetrialandtheownersacceptance.操作方法Methodofoperation序号及步骤名称Serialnumberandstepname主要作业方法和操作要求Mainworkingmethodsandoperationalrequirements工艺质量要求ProcessqualityrequirementsL底座制作所使用的槽钢要求平整,无重皮、残缺现象,且有出厂合格证,材料的型号、规格应符合图纸设计要求Thechannelshouldbesmoothandnoglitchnodeformingwiththecertificationmaterialtypeandsizedesignrequirementsofthedrawings.L盘柜底座制作Panelbaseproduction.制作前材料应进行调平、调直Thematerialbeforemakingshouldbelevelingandstraightening..下料底座尺寸根据图纸设计用无齿锯下料,严禁采用气割下料下料要留出余量,以免制作后总长度小于计算长度,一般每面盘多预留Materialcutting:Basesizeaccordingtothedesignofthedrawingswithno-teethsawcuttingprohibittheuseofgascuttingmaterial.Thematerialshouldbesetasidetoavoidthetotallengthoftheproductionislessthanthelengthofthecalculationgenerallyreservedforperpanel.焊接符合DL/T
5210.7规定WeldingcomplieswithDL/T
5210.7regulations.
4.底座应在施工平台上进行制作,组装时应横平竖直用水平尺、直角尺找平、找正后用电焊点焊,再反复进行检查、调整,整体整洁美观便可焊牢Thebaseshouldbemadeontheconstructionplatformandtheassemblyshouldbehorizontalandvertical.Usehorizontalrulerrightanglerulertofindflatcorrectafterusingweldingspotweldingandthenrepeatedinspectionadjustmentthewholeneatandbeautifulcanbeweldedfirmly
5.盘底座外表面焊口应打磨平整Theoutersurfaceoftheplatebaseshouldbepolishedandflat.操作方法Methodofoperation序号及步骤名称Serialnumberandstepname主要作业方法和操作要求Mainoperatingmethodsandoperationalrequirements工艺质量要求Processqualityrequirements盘底座安装Cabinetbaseinstallation.将盘底座搬运到现场安装位置,搬运存放时轻抬轻放,防止强烈碰撞、振动而产生变形MovethecabinetbasestotheinstallationlocationHandlelightandweightwhencarryingtoavoidstrongcollisionvibrationanddeformation..底座安装应在地面或平台二次抹面前进行Thefloororplatformshouldbesecondfloatedbeforebaseinstallation.根据图纸找出盘的安装中心线,确定底座的安装位置Accordingtothedrawingtofindouttheinstallationcenterlineofthepanelandtodeterminethebaseofinstallationposition..底座安装前,要清理基础地面或基础沟,将预埋的铁件找出,在没有预埋铁的地方,则将固定铁件用膨胀螺栓固定在地面上BeforetheinstallationofthebasetocleanthegroundorfoundationditchandfoundouttheembeddedironpiecesandthentofixtheironwithexpansionboltsonthegroundWhereisnopre-embeddediron.
1.焊缝饱满,水平焊缝打磨后与盘底座高度一致Theweldisfullthehorizontalweldispolishedandtheplatebaseishighlyconsistent..在适当位置放置水准仪,以土建专业二次抹面的标高为基准找平,以检查有无过高之处Takethewaterlevelonappropriatelocationwithcivilengineeringsecondarywipingtheelevationofthesurfaceasabenchmarktocheckforexcessive..盘底座上表面一般应高出最终地面Theuppersurfaceofthediskbaseisgenerallyhigherthanthefinalground.将底座就位,据盘中心线找正,再用水平仪找平,同时以预先准备好的不同厚度的垫铁在底座下进行调整Takingthebaseisinplaceaccordingtothecenterlineofthecabinettofindalignmentandthenusingthewaterleveltofindstandardatthesametimetothedifferentthicknessofthehornpreparedinadvanceunderthebasetobeadjusted..找平后,再校对其中心线,合适后用电焊将底座与预埋件点焊,复查正确无误后将底座与垫铁、预埋铁件焊牢BeforeweldingthebasewiththeembeddedpartsweneedtofindoutthelevelandthentocheckthecenterlineThentorecheckthecorrectionafterthebaseandthehornembeddedironwelding.
2.盘底座接地必须良好,盘底座接地必须至少为两点接地Groundthechassisbasemustbegoodgroundingthebaseofthechassismustbeatleasttwopoints.序号及步骤名称Serialnumberandstepname主要作业方法和操作要求Mainoperatingmethodsandoperationalrequirements工艺质量要求Processqualityrequirements
1.盘柜的运输Containertransport.盘柜吊装前必须进行上报专业申请吊装许可,并对现场进行风险预控评估,出具风险评估报告许可经审批通过后,吊装运输人员经技术员安全、技术交底,并了解工作情况Beforehoistingthecabinetsitmustbereportedthedepartmentapplicationofhoistinglicenseandconductriskpre-assessmentonsiteandissueriskassessmentreport.Approvedbytheapprovaltheliftingoftransportpersonnelbytheengineersafetytechnicalexplanationtounderstandthecondition..盘柜吊运要有专业的起重工指挥起吊Thepanelsliftingmusthaveaprofessionalliftingworkertocommandlifting..运输过程中车辆要缓慢行驶,为防止盘柜设备倾斜、掉下而损坏,用绳索固定盘柜,并由专人监护Duringtransportthevehicleshouldrunningslowlyinordertopreventtheequipmentofthecabinetfromtiltingfallingandbeingdamagedfixingthecabinetwithropesandbeingsupervisedbyaperson..就位时要事先在设备下面加垫方(枕)木,以便抽出吊带Beforeinplacetakepaddingundertheinstallationinordertopullouttheharness..起吊盘柜时,盘柜保持直立,要防止乱晃Whenliftingtheenclosuretheenclosureiskeptuprighttopreventdisorderlyshaking..盘柜运输时必须垂直运输,运输吊装过程中避免碰撞,裸露盘柜应在盘柜与接触物之间填充缓冲物Thecabinetsmustbetransportedverticallyavoidcollisionduringtransporthoistingprocessandtheexposedcabinetshouldbefilledwithbufferbetweenthecabinetandthecontactobject..设备放置牢靠摆放整齐Theequipmentsissecurelyplacedandneatlyarranged.操作方法Methodofoperation序号及步骤名称Serialnumberandstepname主要作业方法和操作要求Mainoperatingmethodsandoperationalrequirements工艺质量要求Processqualityrequirements
1.盘柜定位Cabinetpositioning.将盘柜运至安装地点Movethecabinettotheinstallationsite..盘柜定位时,先根据设计图纸将盘柜逐一对号运至基础上,在底座上把每面盘调整到大致合适位置,由每面盘的固定螺丝孔处向底座上划线及划中心孔,定位各固定螺栓的位置WhencabinetspositioningthefirstaccordingthedrawingsdesigntotakethecabinetstothenumberontheplaceonthebasisofthebaseplatetoadjusteachpaneltoasuitablelocationfromthefixedscrewholesoneachplatetothebaselinemarkedandcenterHolepositioningthelocationofthebolts..将盘搬下,对底座上各固定螺栓位置钻孔控制室、电子间等控制盘柜如有绝缘要求,需在盘底与底座之间加装厚度为10mm的胶皮垫,此橡胶垫可采用10mm厚度的整块橡胶皮根据盘、台底座的形状割出,再在有安装孔的位置打出安装螺丝孔加上绝缘胶垫后再将盘移回底座,拧上螺栓MovetheplateanddrillholesonthefixingboltsonthebaseiftheCCRelectricalbuildingandothercontrolpanelsneedbeisolatedweshouldtoinstallathicknessof10mmbetweenthebottomoftheplateandthebaserubberpadtherubberpadcanbe10mmthickpieceofrubberaccordingto
1.盘台柜的安装应牢固、平整、垂直,盘体无残缺,油漆美观Theinstallationofthepan-cabinetshouldbefirmflatverticalnoincompletediscbeautifulpaint
2.机柜对地绝缘或接地值符合设计、厂家及规范要求Theinsulationorgroundingvalueofthecabinettothegroundconformstothedesignthemanufacturerandthestandardrequirements
4.相邻两盘连接处的盘正面平面度无太大偏差,五面盘以上成排盘面无太大偏差;盘间的连接无明显缝隙Thereisnolargedeviationintheflatnessoftheplateatthejointoftheadjacenttwoplatesandthereisnolargedeviationinthearrangementofthedisksurfaceabovethefiveplates;thereisnoobviousgapbetweentheplatestheplatethebaseofthebaseshapeCutoutandtheninstalltheholeinthelocationoftheinstallationscrewholes.Addinsulationpadsandthenmovebacktothebaseplatescrewonthebolt..单个盘柜的水平调整,可用水准仪测量;单个仪表盘的垂直调整,用磁性线锤,测量盘面上下端与吊线的距离,若上、下距离相同表示此盘面垂直;为保证测量准确,盘的每个面都要进行水平和垂直测量Theleveladjustmentofasinglepanelcanbemeasuredbyspiritlevel;verticaladjustmentofasingleinstrumentpanelwithmagneticplumbmeasuringthedistancebetweentheupperandlowerendofthediskandhangingwireifthesamedistancefromtoptobottomindicatesthatthedisksurfaceisvertical;Makehorizontalandverticalmeasurementsoneachside..成排盘柜找正、调平时,要先精确地调整第一面盘柜,再以第一面盘柜为标准,将其它盘柜逐次调整、定位找正、找平后,再次复查Whentherowofcabinetscorrectingandlevelingwemustaccuratelyadjustthefirstpanelandthentothefirstpanelasthestandardcabinettheothercabinetwillbeadjustedonebyonepositioning.correctinglevelingrecheck..盘柜定位找正时严禁使用手锤直接敲打盘面,应加垫厚胶皮或木板,以免损坏油漆及设备Whenpositioningthecabinetsitisstrictlyforbiddentousethehandhammertodirectlybeatthedisksurface.Thethickrubberorwoodpaddingshouldbeaddedtoavoiddamagedthepaintandequipment.安监Safetysupervision签名signature日期date总工ChiefEngineer签名signature日期date:
2.盘柜固定Cabinetfixed.盘柜定位符合工艺质量要求后,将盘柜固定牢固将盘柜底部与底座间的连接固定螺丝尽量同步锁紧,使得四角受力平衡,避免由于固定螺栓锁紧程度不同而引起盘柜左右或前后倾斜Afterthepanelspositioningmeetthequalityrequirementsoftheprocessthepanelcabinetwillbefirmlyfixed.Asfaraspossibletheconnectingscrewsbetweenthebottomoftheenclosureandthebaseshouldbelockedsynchronouslysoastobalancethestressonthefourcornerssoastoavoidtiltingtheleftorrightorfrontandrearoftheenclosureduetothedifferentdegreeoflockingofthefixingbolts..成排的盘柜,需将相连接的侧面用连接螺栓加以紧固Rowofpanelsweneedtoconnectthesidewiththefasteningboltstobeconnected..固定过程中要反复对盘的每个面进行水平和垂直测量,若距离偏差超出工艺要求则要重新加以定位Duringthefixingprocesshorizontalandverticalmeasurementsshouldbemadeoneachsideofthediskrepeatedly.Ifthedistancedeviatesbeyondtheprocessrequirementsitmustberepositioned..连接螺栓、垫片及弹簧垫圈防锈层完好Connectingboltsgasketsandspringwashersrust-prooflayerintact..盘台柜的固定应牢固、平整、垂直Pantablecabinetsshouldbefixedflatvertical.
3.防腐补漆Anti-corrosionpaintrepair检查盘底座和接地扁铁防锈漆、银粉漆有无缺漏或破坏,若有进行补漆Checkplatebaseandgroundflatironantirustpaintsilverpaintthereisnoomissionordamagedifthenaint油漆均匀、完整、美观Thepaintisuniformcompleteandbeautiful.单位工程名称projectname盘柜安装分部工程名称Divisionprojectname工程编号ProjectNumber验收时间AcceptanceTime年月日序号NO.检验项目Testitems执行情况Implementation相关资料Relevantinformation123456789职业健康安全危害与风险/环境因素和影响识别OHSHazardRisk/EnvironmentalAspectImpactIdentification初始风险的控制措施ControlMeasuresforInitialRisks初始风险指数InitialRiskIndex对应风险控制措施ControlMeasuresforResidualRisks剩余风险指数ResidualRiskIndex控制措施负责人PersonIn-ChargeforControlMeasures编号S/N过程/工作活动Process/WorkActivity职业危害.环境方面OHSHazardEnvironmentalAspectOHS风险环境影响OHSRiskEnvironmenta1Impact现有的控制措施ExistingControlMeasures严重性Severity可能性Likelihood风险级别RiskLevel其他控制措施AdditionalControlMeasures可能性LikelihoodoAuq1a负责人姓名/名称/签名PersonIn-ChargeName/Designation/Signatur1电动工器•电气危险•受伤/死亡L为工人提供适当的
3391.定期检查切割、326具转动使•用工具切•噪声污染PPE;包括面罩,耳塞等打磨工器具,并用割•Injuries/
2.在工人开始工作前对做好检验记录•火灾Fatalities其进行指导;确保工人知
2.督促操作人员.噪音的产•Noise道工作的危险遵循安全规章生Pollution
3.在使用前先检查切割
1.Regular•Electrical和研磨工具,以确保其inspectionofHazards状态良好cuttingand•Cutby
4.在开始工作前清除周grindingtoolsandtools.围的易燃物markthem.•Fire
1.ProvideproperPPEfor
2.Urgeoperators•Generationtheworkers;includefacetofollowsafetyofNoiseguardearplugetc.regulations.
2.Conductinstructiontotheworkersbeforetheystartwork;ensuretheworkersknowthehazardsofthejob.Checkthecuttingandgrindingtoolsbeforeusethemtoensuretheyareingoodcondition.Clearthesurroundingcombustiblesbeforestartwork.2起吊作业Settingupofmobilecrane.施工地面不平整腿部支撑垫不当车轮不离开地移动式起重机的漏油•Unevennessofthegroundat•受伤/死亡土壤污染Injuries/Fatalities.SoilPollution.检查现场情况;确保用于设置起重机的地面平整.为移动起重机的支腿提供适当的支撑垫.确保车轮在腿部支撑后离开地面.在使用前检查移动起重机的状态,确保没有漏油
1.Checktheworksitecondition;Makesurethe
326.督促施工人员严格采取控制措施.督促操作人员遵循安全规章.督促操作人员规范施工
1.Supervisetheconstructionpersonneltotakecontrolmeasuresstrictly.313worksiteLegsupportpadsimproperThewheelsdontleavethegroundOilleakageofmobilecranefloorisflatforsettingupthecrane.Providepropersupportpadsforthelegofmobilecrane.Ensurethewheelshaveleftthegroundafterthelegspropup.Checktheconditionofthemobilecranebeforeuseitensurethereisnooilleakage.Superviseoperatorstofollowsafetyregulations.Supervisetheoperationpersonneltostandardizetheconstruction3索具的载荷和结构Riggingofloadandstructure•负载和结构的索具不当•负载落下•Riggingofloadand•受伤/死亡•Injuries/Fatalities.通过正确的方式捆绑负载或结构,确保它被绑紧.只有被授权的操作员可以这样做.确保索具都处于良好
326.开始提升前,严格检查负载和结构的捆绑情况.定期检查索具,并标记.督促操作人员313structureisimproper•Theloadfallsdown状态
4.结构的边缘采取保护措施Bundlingtheloadorstructureintherightwayensuresthatitistightlybound..Onlytheauthorizedriggercandothis.Ensuretheriggingsareingoodcondition.Takeprotectionmeasuresfortheedgeofstructure.遵循安全规章Beforestartingtheupgradestrictlycheckthebindingoftheloadandstructure.Regularinspectionoftheriggingsandmarksthem.UrgetheoperatorfollowtheSafetyregulations4机器移动Movingofmachine•工人被移动机械击中•Workerhit・受伤/死亡Injuries/Fatalities.设置专人以指挥移动机械.设置隔离区,防止不相关人员进入危险区域
2241.严格现场监督检查
2.督促操作人员遵循安全规章212bymovingmachinery.只有授权操作员才能操作机器.开始工作前对工人进行指导;确保工人知道危险Setbankmantocommandthemovingmachinery.Setupisolationareatopreventunrelatedpersonnelfromenteringtheriskarea.Onlytheauthorizedoperatorcanoperatethemachine.Conductinstructiontotheworkersbeforestartwork;ensuretheworkersknowthehazards.3•督促操作人员正确的使用机器Stricton-sitesupervisionandinspection.UrgetheoperatorfollowSafetyregulations.Urgethebankmancommandthemachineproperly.5高空作业Workingontheheight•高空坠落高空坠物击中FallfromheightStruckbyfallingobject・受伤/死亡Injuries/Fatalities.开始工作前对工人进行指导;确保工人知道在高空作业的危险.为工人提供适当的安全带,并要求他们正确地佩戴安全带.高平台保护到位.将小材料和工具放入袋子或工具箱中,防止物体掉落.在开工前申请高空作业许可证,并确保预防措施到位Conductinstructiontotheworkersbeforestartwork;ensuretheworkersknowthehazardsofworkingontheheight.Providepropersafety
326.禁止高空作业的违规行为,在发现违规行为时立即停止工作.在进入高空平台作业时,携带攀爬自锁装置.在高空作业区域下设置隔离控制区域Prohibittheviolationbehaviorofworkingatheightstopworkimmediatelywhilefindviolationbehavior.Setclimbing313hardnessfortheworkerandaskthemwearthehardnessproperly.Thehighplatformprotectionisinplace.Putthesmallmaterialsandtoolsinbagortoolboxtopreventobjectsfalling.Applyworkingatheightpermitbeforestartworkandensurepreventionmeasuresareinplace.self-lockingdevicewhengototheheightplatform.
3.Setisolationcontrolareaundertheheight.6防坠落装置的使用Useoffallarrestsystem•防坠落设施使用不当•Thefallarrest.高空坠落•受伤/死亡FallfromtheheightInjuries/.开始工作前检查防坠落器使用到位.确保其制动系统是否完好,无破损.确保他们正确地使用
3261.严格的现场监督检查2督促施工者遵循安全规章
3.定期检查防坠313systemimproperFatalities防坠落装置Checkthefallarrestsystemistakeninplacebeforestartwork.Ensurethearrestsystemisingoodconditionnodamage.Conductinstructiontothelabors;ensuretheyusethefallarrestsystemproperly.落装置Stricton-sitesupervisionandinspection.Urgetheoperatorstofollowthesafetyregulations.Regularinspectthefallarrestsystem.7架子的搭设Erectionofthestructure•结构的不稳定性•Instabilityofthestructure架子倒斜受伤/死亡SlantingdownofstructureInjuries/Fatalities.采取措施加固结构,防止其倾斜.设置隔离区,防止不相关人员进入危险区域Takemeasurestoreinforcethestructuretopreventitfromtilting.Setupisolationareato326L严格遵循安全规章
2.审查固定方案,确保它是正确的
1.Urgetheoperatorstofollowthesafety313preventunrelatedpersonnelfromenteringtheriskarea.regulations.
2.Reviewthefixedplanandmakesureitiscorrect.8手拉葫芦的使用Useofchainblock•超载使用•链块损坏OverloadinguseThechainblockisdamaged.受伤•Injuries.对劳动者进行指导,让他们知道如何使用倒链.在使用前检查链条块以确保其状态良好.当操作员拉葫芦链时不要使用太多的力气.操作完成后锁定Conductinstructiontothelaborslettheyknowhowtousethechainblock.Checkthechainblockbeforeuseittoensureitis
224.敦促工人遵守安全操作规程.滑轮链组的定期检查.严格的现场监督检查Urgetheworkersfollowthesafetyoperatingprocedure.Regularinspectionofthechainblock.212ingoodcondition.Dontusetoomuchstrengthwhenoperatorthechainblock.Lockitafteroperating.
3.Stricton-sitesupervisionandinspection.9焊接作业Weldingwork•火灾/爆炸・触电危险Fire/ExplosionElectricalHazards•受伤/死亡•Injuries/Fatalities.在工人开始工作前对其进行培训;确保工人知道工作的危险.为工人提供适当的PPE;包括防护面罩、围裙等.在施工区域放置灭火器.在开始工作前清除周围的易燃物,并在施工区域设置防火毯
5、作业前检查焊机,确保其完好
326.施工负责人督促施工人员严格遵守安全规章.焊机必须定期检查并做好标记
1.Constructionsupervisorurgesconstructionpersonneltostrictlycomplywithsafetyregulations3136焊机接地良好,.焊工必须持证上岗•焊接作业前应有动火作业许可Conductinstructiontotheworkersbeforetheystartwork;ensuretheworkersknowthehazardsofthejob.ProvideproperPPEfortheworkers;includefaceguardweldingclothetc.Provideproperfireequipmentattheworksite.Clearthesurroundingcombustiblesbeforestartworkandsetfireblanketattheworksite.
2.Regularinspectionoftheweldingmachineandmarksthem.*Checktheweldingmachinebeforeuseitensureitisingoodcondition.Thegroundingofweldingmachineisgoodandtheeclecticcableisnotdamaged.Onlythespecialweldercanoperation.Applyhotworkpermitbeforestartwork.10雷击/中暑Lightningstrike/Heatstroke・雷电・高温.Lightning•hightemperature
1.雷雨大风天气严禁在锅炉高空作业,防止雷击及高空坠落Thunderstormgaleweatherisstrictlyprohibitedintheboiler
326.实时关注气象信息,避免雷雨大风天气在室外施工.备好中暑急救用品
1、Immediate313high-altitudetopreventlightningandhigh-altitudefall.
2.夏季施工做好防暑降温工作,防止施工人员中暑Summerconstructioncompletescoolingworkpreventstheconstructionpersonnelheatstroke.attentiontometeorologicalinformationavoidthunderstormgaleweatherinoutdoorconstruction
2、Prepareemergencysuppliesforheatstroke.名称Description型号规格typespecification单位Unit数量Quantitys备注RemarksDCS机柜800X800X2300WXDXH面PC23电磁阀箱600X300X1000WXDXH面PC14DCS操作台800X1100X750WXDXH面PC26保护箱1600X600X1800WXDXH面PC8操作台600X1100X750WXDXH面PC8电源柜800X600X2200WXDXH面PC10电磁阀箱600X300X800WXDXH面PC4泵控制箱600X450X1400WXDXH面PC5接线盒JFBX-30面PC3制氢站柜1000X1000X2000WXDXH面PC3主要设备交货条件Majorequipmentdeliveryconditions到货需开箱验收,确保盘柜外观无破损变形设备型号符合设计要求,出厂资料齐全Uponarrivalunpackingandacceptanceisrequiredtoensurethattheappearanceofthecabinetisnotdamagedordeformed.Theequipmentmodelmeetsthedesignrequirementsandthefactorydataiscomplete.作业环境及应具备条件Workingenvironmentandconditions.场地、力能:Sitepower使用专业施工平台进行盘底座制作;盘柜安装需电子间、集控室土建完成;高空作业面搭设脚手架、防护栏及安全网,交叉作业面有隔离板或棚场地要求平整清洁、进出通道畅通Tousetheprofessionalconstructionplatformforproductingofpanelbase;whenthePanelinstallingmakesuretheelectronicequipmentroomcentercontrolroomofcivilconstructionworkdone;whenworkingathighweshouldtotakefalseworkprotectiverailsandsafetynetsWithisolationboardorshedtocross-operationworkingTheworkingspaceshouldbecleanandaccessible..环境Condition室内所有土建工程施工完毕且验收合格,屋顶无渗水现象TomakesureallthecivilconstructionworkhadcompletedandhadinspectedtheQCinspectionpassedtheroofisnotleaking.控制室墙壁、柱子、顶棚的粉刷、空调的风道及照明施工完成Makingsurethewallspillarsceilingpaintairconditioningductandlightingconstructioniscompletedofcontrolroom.现场清理干净且所需的材料、工具准备齐全Keepthesitecleaningandmakesurealltherequiredmaterialstoolsareprepared.确认现场施工电源具备Tobesurethepowersupplyavailable.施工区域光线充足,光线不充足地方安装照明设施Theconstructionareaislightenoughandifnottoinstalllighting.工期Duration根据库尔纳项目部施工计划安排,按图纸设计和设备到货情况,热控盘柜安装在2020年12月开始施工,至2021年8月份竣工AccordingtotheconstructionplanoftheKhulnaProjectDepartmentaccordingtothedesignofthedrawingsandthearrivaloftheequipmenttheinstallationofthethermalcontrolpanelwillstartconstructioninDecember2020andwillbecompletedinAugust
2021..人力Human.Resources技术员具有识图能力及盘柜安装经验1名全面负责盘台、箱、柜安装的技术管理工作;安全员1名全面负责施工中的施工安全;班组长1名负责组织安排施工人力、物力;持证电工和焊工各1名负责电源接线和焊接工作负责盘底座制作、安装、盘柜运输、安装的安装工4名Engineerwiththeabilitytomapandenclosureinstallationexperience1persontoberesponsibleforplatformboxcabinettheinstallationoftechnicalmanagementworksecurity1officeroftheoverallresponsibilityforconstructionsafety;TheteamLeader1toberesponsiblefororganizingtheconstructionmanpowerandmaterialresourcesthecertificateelectricianandtheweldereach1areresponsibleforthepowerwiringandtheweldingwork.Toberesponsiblefortheproductioninstallationenclosuretransportinstallationof4workers.注Notice所有施工人员都必须经三级安全考试合格后方可上岗Alltheconstructionpersonnelmusttopassthethreelevelsafetyexaminationbeforeworking.机械Mechanical运输车辆1辆、吊车1辆、焊机2台、托盘车2台、2吨手拉葫芦2个1vehicles1crane2Electricwelderspallettrucks22tonhandhoist工器具Tools电源盘4个、水平仪1台、磨光机2台、水平尺2把、直角拐尺2把、钢卷尺2把、无齿锯2把、冲击钻1把,手提电钻2把,锤子2把、磁性线锤2个、扳手4把、锯弓2把、垫木2块4Powersupplies!spiritLevel2polisher2Levelbarrightangleturnruler2steeltapemeasure22noteethsaw1Impactdrill2portableelectricDrill2hammermagneticlinehammer24wrenchsawbow22padding.注计量器具及电动工具需校验或检验合格后方可使用Measuringinstrumentsandelectricpowertoolsneedtobecalibratedorinspectedbeforebeingused.材料Material[
6.3槽钢、M10x80mm固定膨胀螺栓、M10x35mm连接螺栓、610绝缘胶垫、防锈漆、银粉漆、焊条、扁铁、无齿锯片、磨光机片、锯条、钻头等[
6.3channelsteelMIOx80mmexpansionboltsMIOx35mmjointbolts610rubberpadsantirustpaintsilverpaintweldingrodflatironno-toothsawbladespolishingmachinessawbladesbitsandsoon.注材料质量、型号规格要符合要求、国家质量标准Materialqualitymodelspecificationstoconformtherequirementsnationalqualitystandards.。